How to estimate actual production capacity
Calculate good shift output using demonstrated running speed, available time and first-pass yield, with a worked manufacturing example.
Rated output is a starting point
A nameplate speed of 100 units per minute implies 48,000 units in an eight-hour shift only if the line runs at that speed for the entire shift with no rejects. Use demonstrated operating conditions when planning commitments.
A worked shift example
Illustrative example: subtract one hour of stops and changeovers from an eight-hour shift. Seven running hours × 60 minutes × 80 units per minute = 33,600 units. At 95% first-pass yield, that becomes 31,920 good units. Rework is excluded.
Avoid counting losses twice
If demonstrated running speed already reflects slower operation, do not subtract the same speed loss again. Likewise, subtract planned time once. Check your estimate against actual good output across representative shifts.
Use the weekly calculator
The calculator on our homepage uses units per hour. Enter 4,800 units per hour for 80 units per minute. Enter the schedule and losses for your own operation; its defaults are an example.
Video transcript
A machine rated at one hundred units a minute doesn't guarantee forty-eight thousand units in an eight-hour shift. Here's an illustrative example. Lose one hour to stops and changeovers. Run the remaining seven hours at eighty units a minute. That's thirty-three thousand six hundred units. At ninety-five percent first-pass yield, you get thirty-one thousand nine hundred twenty good units. Plan with demonstrated output. Follow Manufacturing Margin for better manufacturing decisions.
AI-generated narration. Numerical examples are illustrative and are not client results.